|
|
|
Trinity Center for Women and Girls
In Sports
Construction Photos
August 2002
|
|
Scaffolding fully surrounds the Trinity Center for
Women and Girls as construction continues at a swift
pace from top to bottom! Nearly 120,000 bricks are being
installed to create the exterior finish, along with
precast concrete. The roof is completely enclosed with
layers of insulation and an ice and water shield, and
is being prepared for the installation of 45,000 red
clay tiles. In the gymnasium, scaffolding has been erected
for the installation of electrical wiring and the sprinkler
system. Railings are being installed along the walking
track, and windows will soon be installed in the arches.
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| Inside, the pool and spa have
been excavated and are being completed with gunite, plaster
and tile. The concrete slab around the pool has been poured,
and all of the pool filters have been installed. Tile
is being installed in the men's locker room (below). |
 |
 |
 |
 |
 |
 |
| In the Fitness Center in the
sub-basement of Alumnae Hall, drywall is being installed;
wall sconces have been installed and the ceiling has been
painted - and has been completed with a drop grid ceiling.
Tile is being installed in the restrooms and wet training
room. Finishing touches are being added, including Corian
windowsills, and purple and gold paint on the angled columns.
|
 |
 |
 |
 |
 |
 |
| |
| |
|
| |
|
| |
|
| |
|
| |
|
|